Renovation Status and such
Called the building inspector for an "insulation inspection". He'll come out tomorrow to make sure that we've property applied the insulation in the ceiling of the dining room. I'm not sure why the code says that it has to be inspected.
I've selected the electrician for the project and he is going to start working on the permit, which should take about 1 1/2 weeks. Just in time for my return from Ireland.
I've told one of the HVAC bidders that his proposal was too high. Let's see what he comes back with.
The plumber came out today to see what is under the existing floors (yes, we had to remove about 60 feet of plywood flooring and dig up a cement floor in an existing bathroom.)
Our ADA compliant ramp is in place. We've started putting up a few of the frames for the interior walls.
Picture of the ADA compliant ramp.
View of the dining room from the bar section.
We finished removing an eight inch thick concrete ceiling in the old mechanical room. It took almost a week to remove the ceiling (about 10 x 7 feet). It took a long time because we had to remove it in small pieces for the safety of the people removing it.
We started scraping the old paint from the balcony today. Tomorrow we'll start the construction of the new railings.
I ordered 40 chairs for the restaurant. Mahogany colored beechnut chairs with a green vinyl cushion. I also purchased a used ice/blender station for the bar. I'll pick it up on Monday or Tuesday after they clean it up a bit.
I've selected the electrician for the project and he is going to start working on the permit, which should take about 1 1/2 weeks. Just in time for my return from Ireland.
I've told one of the HVAC bidders that his proposal was too high. Let's see what he comes back with.
The plumber came out today to see what is under the existing floors (yes, we had to remove about 60 feet of plywood flooring and dig up a cement floor in an existing bathroom.)
Our ADA compliant ramp is in place. We've started putting up a few of the frames for the interior walls.
Picture of the ADA compliant ramp.
View of the dining room from the bar section.
We finished removing an eight inch thick concrete ceiling in the old mechanical room. It took almost a week to remove the ceiling (about 10 x 7 feet). It took a long time because we had to remove it in small pieces for the safety of the people removing it.
We started scraping the old paint from the balcony today. Tomorrow we'll start the construction of the new railings.
I ordered 40 chairs for the restaurant. Mahogany colored beechnut chairs with a green vinyl cushion. I also purchased a used ice/blender station for the bar. I'll pick it up on Monday or Tuesday after they clean it up a bit.